Maharashtra Industrial Development Corporation (MIDC)
Maharashtra Industrial Development Corporation
Government of Maharashtra
Maharashtra's state industrial infrastructure agency — it allots industrial plots, built-up space and small sheds through the MILAAP portal, and runs the MIDC Grand Challenge.
MIDC at a glance
| Full name | Maharashtra Industrial Development Corporation |
|---|---|
| Part of | Government of Maharashtra |
| Established | 1962 |
| Address | "Udyog Sarathi", Marol Industrial Area, Mahakali Caves Road, Andheri (East), Mumbai – 400 093, Maharashtra |
| Programmes | 2 standing programmes |
| Stages supported | Idea, Prototype, MVP, Early revenue, Growth |
| Equity | None taken — all 2 programmes that state a policy |
| Official website | midc.maharashtra.gov.in |
| investor@midcindia.org |
Programs by Maharashtra Industrial Development Corporation (MIDC)
1 past program · Filter all programs
What's next?
This round has ended. Tap Notify me and we'll email you when the next one opens.
Programs Maharashtra Industrial Development Corporation (MIDC) supports
Programs this organisation co-organises, run by others. · 1 open now · 0 past
Programmes they run
Standing programmes at Maharashtra Industrial Development Corporation (MIDC), separate from the funding calls above.
MIDC is not an incubator and runs no cohort. These are the two routes it actually publishes that a business can apply through. The Grand Challenge microsite's landing page lists a different set of five challenge areas from its own challenges, about and FAQ pages, which agree with each other; the detail pages are used here. MIDC's site and our own cohort record also give different closing dates for the 2026 edition, so confirm the deadline with MIDC before planning around it.
MIDC Grand Challenge
CompetitionAn open call for solutions to five named operational problems across MIDC's industrial estates, where selection means being funded to deploy the solution at an MIDC site.
Best for: Startups, MSMEs, companies, individual innovators, students, institutions and consortiums with a deployable solution to an industrial infrastructure problem
- Idea – Growth
- Hybrid
- No equity
- Grant support for selected startups
What you get, who can apply and how to applyHide details
A pan-India call by MIDC for solutions to five named operational problems across its industrial estates: pothole detection and durable repair, carbon capture and emission management and trading, wastewater and effluent treatment and desalination and waste recycling, renewable and sustainable green energy, and AI-driven solutions for industrial infrastructure. MIDC is explicit that this is not an ideas competition — selection is a mandate to implement your solution at a designated MIDC site.
What you get
- An implementation mandate to deploy your solution at a MIDC site, with MIDC funding the deployment itself
- Payment in four milestone-linked phases: mobilisation on signing the implementation agreement, deployment, verified commissioning and sign-off, and a final phase after one year of validated performance
- Your pre-existing work stays yours
Who can apply
- Startups including DPIIT-recognised ones, MSMEs, companies and LLPs and other registered business entities
- Individual innovators, entrepreneurs and professionals
- Students and student teams at undergraduate, postgraduate and doctoral level
- Academic and educational institutions, R&D institutions and laboratories, incubators and accelerators, non-profits and Section 8 companies, and industry associations
- Joint consortiums of any of the above, with one nominated lead applicant
- Foreign entities, independently or with an eligible Indian partner, subject to law
- You must be legally competent to contract with MIDC, hold valid statutory registrations where they apply and a valid PAN, and not be blacklisted or debarred by any government authority
- There is no restriction on team size, and no minimum turnover or prior government-project experience at the ideation stage
- One problem statement per applicant or team — applying to more can disqualify all your applications
How selection works: applications are scrutinised against the eligibility criteria and for completeness, and incomplete or non-compliant ones may be rejected there. Eligible applications go to a Finale, where shortlisted applicants may be asked to present, demonstrate or clarify their solution before MIDC and its nominated evaluators. Selected solutions are then deployed at a designated MIDC site.
How to apply: submit the online application form with all required documents before the closing date, with a two-page executive summary and a ten-page detailed proposal. Queries go to grandchallenge@midcindia.org.
Note on ownership: anything you develop using MIDC's problem statements, sites, funding or resources, and every physical asset created during implementation, vests with MIDC. Read that clause before you apply.
MIDC's standing allotment route for industrial plots, built-up space and small sheds across Maharashtra, applied for on the MILAAP portal.
Best for: Businesses setting up or expanding a manufacturing, processing or logistics unit in Maharashtra, including small units looking for a shed
- Continuous — no intake window
- In person
- Paid, no equity
What you get, who can apply and how to applyHide details
MIDC's standing route to industrial property in Maharashtra. Everything is applied for on MILAAP, the MIDC Industrial Land Application and Allotment Portal. It is an allotment process, not a startup programme — there is no cohort, no mentoring and no deadline, and you pay for what you get.
What you get
- A developed industrial plot on a 99-year lease, with roads, water supply and street lighting, and in some areas a common effluent treatment plant
- Or built-up space, built for specific industry sectors and available in specific locations
- Or an industrial shed, which MIDC says is normally aimed at the small scale sector and runs about 1,000 to 2,000 sq.ft, in select locations
- Water supplied and billed by MIDC, and Single Window Clearance for the permissions that follow
Who can apply
- Direct Allotment is only for priority categories: Mega and Ultra Mega projects, Davos MoUs, Magnetic Maharashtra MoUs, government-level MoUs, and central or state public sector undertakings
- e-Bidding for industrial plots is the open route, described by MIDC as a platform for entrepreneurs to bid on plots
- e-Bidding also covers residential and commercial plots
- MIDC publishes a priority provision it attributes to the state's Industrial Policy 2019, reserving a share of area in new industrial estates for SC/ST entrepreneurs and for women entrepreneurs and units of women's savings groups
How selection works: applications from both routes are scrutinised by members of the Land Allotment Committee after a review of your Detailed Project Report. The committee meets online, you are invited by email, and MIDC states its decision is final. Plots under e-bidding go to the highest qualified bidder once bid documents have been scrutinised and the committee's report approved by the Joint CEO. Bids are capped at 125% of the base rate and quoted rates are revealed only after technical qualification.
How to apply: log in to MILAAP, open the module for the route you want, fill and submit the application form and pay the processing fee online. You will need a Detailed Project Report, the constitution of the applicant and a block plan. A submission ID is generated and a committee date comes by email. If approved, you receive an offer letter, pay earnest money within fifteen days, receive the allotment order, pay the balance occupancy premium within thirty days, execute the agreement to lease and take possession with an MIDC surveyor. Building plans then go through an appointed architect on MIDC's approval system, and construction must finish and production begin within three years from possession in A and B zones, five in C and seven in D and D+ zones.
Support services
Help offered alongside funding and space.
MIDC offers no legal, finance or market-access support of any kind — what it provides is permissions, infrastructure and land information.
Regulatory support
Single Window Clearance for pre-operations and post-operations permissions — land applications, lease and mortgage permissions, water and drainage connections, building plan approval, fire NOC, occupancy certificates, transfers and change of land use.
Business advisory
An Investor's Helpdesk staffed by marketing officers and Maharashtra Investment Fellows, reachable on a toll-free number and by email, plus published land bank, land rate and GIS information.
How to apply to Maharashtra Industrial Development Corporation (MIDC)
Work out which door you need
MIDC has two very different application routes and they share almost nothing. If you want land, space or a shed to build in, that is the MILAAP portal. If you have a technology solution to an industrial infrastructure problem, that is the Grand Challenge. There is no incubation programme, no grant window and no desk space, so if that is what you are after, look elsewhere first.
Applying for land or a shed
- Check which allotment route you actually qualify for before you start. Direct Allotment is limited to a short list of priority categories — mega and ultra mega projects, MoUs signed with the state, and public sector undertakings. Everyone else bids.
- In e-bidding the highest qualified bid wins, and bids are capped at 125% of the published base rate. Look up the base rate for the area on MIDC's land rates pages before you decide what to quote.
- The Detailed Project Report is the document your application lives or dies on. It is what the Land Allotment Committee scrutinises, and MIDC states the committee's decision is final, so put the effort there rather than into the form.
- Budget the timeline, not just the money. Earnest money is due within fifteen days of the offer letter and the balance premium within thirty days of the allotment order. Extensions exist but carry delayed payment charges.
- Look at the taluka classification before you pick a location. Zones A through D+ decide both the incentives available and how long you have to build — three years from possession in A and B, five in C, seven in D and D+.
- Small manufacturers should ask specifically about sheds rather than plots. They are a separate category, aimed at the small scale sector, and available only in some industrial areas.
- If you are an SC/ST or woman entrepreneur, ask the helpdesk how the priority allotment reservation is applied in the estate you want. MIDC publishes the reservation but not the mechanics.
Applying to the Grand Challenge
- Pick one problem statement. You may apply to only one, and applying to more can disqualify all of your applications.
- Read the two tracks and say which one you are in. Track A is for an idea, concept or early prototype; Track B is for an MVP, proof of concept, pilot deployment or something already commercial. The applicable track is set by the problem statement, not by you.
- Nothing is reserved for large companies. MIDC states there is no minimum turnover and no prior government-project experience needed at the ideation stage — capacity is assessed later, before implementation.
- Prepare the pitch material properly: a two-page executive summary and a ten-page detailed proposal, plus the registration, PAN, GST and DPIIT or Udyam certificates that apply to you, an authorisation letter, a technical proposal and a signed declaration. A demo video and a product link are optional but help.
- Disclose any existing IP or prior deployment of your solution. MIDC says undisclosed prior IP or deployment can disqualify you even after selection.
- Understand what you are agreeing to. Selection is an implementation mandate, paid out in four phases tied to mobilisation, deployment, commissioning and a performance check one year later, and MIDC can withhold or cut a phase if milestones are missed. Your pre-existing IP stays yours, but anything you develop under the challenge, and the physical assets you build, vest with MIDC.
- Send questions to the challenge inbox rather than the general helpdesk: grandchallenge@midcindia.org.
General
- MIDC's site defaults to Marathi on many pages, with English served under a separate path. Several policy documents and notices are published only in Marathi.
- Dates on the challenge site do not all agree, and the landing page lists challenge areas that the detail pages do not. Treat the detailed pages as the ones to trust, and confirm the closing date with MIDC before you plan around it.
About Maharashtra Industrial Development Corporation (MIDC)
The Maharashtra Industrial Development Corporation (MIDC) is the Government of Maharashtra body that develops and runs industrial land across the state. It was established in 1962 under the M.I.D.C Act 1961, describes itself as the nodal investment promotion agency under the state government, and acts as a Special Planning Authority inside the industrial areas it builds. Its head office is at Udyog Sarathi in the Marol industrial area of Andheri East, Mumbai.
MIDC is not an incubator and it runs no cohort. It does not mentor, invest or take equity. What it offers a founder is a place to build: serviced industrial land, built-up space and small sheds, with the roads, water, drainage, lighting and permissions that go with them. If you are setting up a plant, a workshop, a food processing unit or a warehouse in Maharashtra, MIDC is usually the landlord you apply to. If you are looking for a programme, a grant round or desk space, this is the wrong door.
What you can apply for
There are three kinds of property. Developed plots in industrial areas come on a 99-year lease, with roads, water supply and street lighting already in place, and in some areas a common effluent treatment plant and common facilities buildings. Built-up space is put up by MIDC for specific industry sectors and is available only in certain locations. Industrial sheds are the small end: MIDC says these are normally aimed at the small scale sector and run about 1,000 to 2,000 sq.ft, again in select locations. That shed category is the one most small manufacturers and early hardware businesses end up looking at.
Separately, MIDC occasionally publishes Expression of Interest notices inviting proposals from entrepreneurs for industrial purposes at specific new locations. These sit on its Important Notices page, are usually location-specific, and are often published in Marathi.
How land allotment works
Applications go through MILAAP, the MIDC Industrial Land Application and Allotment Portal. There are three routes on it. Direct Allotment is reserved for priority categories only, which MIDC lists as Mega and Ultra Mega projects, Davos MoUs, Magnetic Maharashtra MoUs, government-level MoUs and central or state public sector undertakings. Most businesses will not qualify for that route. e-Bidding for industrial plots is the open one, described as a platform for entrepreneurs to bid on plots, with bids capped at 125% of the base rate and quoted rates revealed only after technical qualification, so the highest qualified bid wins. A third route covers residential and commercial plots by the same bidding method.
Whichever route you take, you log in to MILAAP, pick the module, fill the application form, pay the processing fee online and get a submission ID. A Detailed Project Report, the constitution of the applicant and a block plan are among the documents required. MIDC then scrutinises the report and puts the application to a Land Allotment Committee, which meets online and whose decision MIDC states is final. If it approves, an offer letter follows and earnest money is due within fifteen days, then an allotment order, then the balance occupancy premium within thirty days, then the agreement to lease, then possession with an MIDC surveyor on site.
After that the obligations start. Building plans go through an appointed architect on MIDC's building plan approval system, with a stated turnaround of 35 days, and construction has to finish and production start within a set period that depends on how developed the taluka is — three years from possession in A and B zones, five in C, and seven in D and D+ zones. Occupancy certificate first, final lease after.
Who can apply
For land, the gate is the route rather than the applicant type: e-bidding is open to entrepreneurs, direct allotment is not. MIDC's own pages also record a priority provision it attributes to the state's Industrial Policy 2019, under which 20% of the area in new MIDC industrial estates goes to SC/ST entrepreneurs and 5% to women entrepreneurs and units of women's savings groups, capped at 25% in total. MIDC's pages still route MSME, SC/ST and women entrepreneurs to that 2019 policy for eligibility and incentives, while its policy library also lists a Maharashtra Industries, Investment and Services Policy 2025. Nothing on the site says which now governs, so check before you rely on either.
The MIDC Grand Challenge
The one thing here that looks like a startup programme is the MIDC Grand Challenge. It is a pan-India call for solutions to five named operational problems across MIDC's estates, and its eligibility is unusually wide: startups including DPIIT-recognised ones, MSMEs, companies and LLPs, individual innovators, students and student teams, academic and R&D institutions, incubators, non-profits, industry associations and consortiums, with foreign entities allowed independently or with an Indian partner. It is worth reading closely before applying, because winning is not a prize — it is a mandate to build the thing at an MIDC site, and the intellectual property you create doing it goes to MIDC.
Services and support
MIDC runs a Single Window Clearance system covering pre-operations and post-operations permissions — land applications, mortgage and lease permissions, water and drainage connections, building plan approval, fire NOC, occupancy certificates, transfers, sub-letting and change of land use. It publishes a land bank showing availability by industrial area, current land rates by regional office and area, and an enterprise GIS with plot-level maps. An Investor's Helpdesk staffed by marketing officers and Maharashtra Investment Fellows takes queries on a toll-free number and by email.
Where it works, and who runs it
MIDC states it has built 300 industrial areas across Maharashtra. Its declared focus sectors are aerospace and defence, automobiles, chemicals, electronics, food processing, gems and jewellery, information technology, leather and footwear, oil and gas, pharmaceuticals, textile and toys. Regional responsibility sits with deputy chief executives for Mumbai, Pune, Marathwada and Vidarbha. The corporation is headed by a Chief Executive Officer from the IAS, currently Shri Deependra Singh Kushwah, with three joint chief executive officers under him. MIDC publishes its recruitment separately on its own recruitment portal, and its tenders on a vendor portal.
Get in touch
Send a message to Maharashtra Industrial Development Corporation (MIDC) — we'll forward it on your behalf.
Who they work with
Sectors
Tags
The team
Shri Deependra Singh Kushwah, IAS
Chief Executive Officer
Dr. Kunal Khemnar
Joint Chief Executive Officer - 1 (Admin)
Smt. Varsha Thakur-Ghuge
Joint Chief Executive Officer - 2
Shri Ajit Kumbhar
Joint Chief Executive Officer - 3
Frequently asked questions about Maharashtra Industrial Development Corporation (MIDC)
What is the full form of MIDC?
MIDC stands for Maharashtra Industrial Development Corporation.
What is Maharashtra Industrial Development Corporation (MIDC)?
Maharashtra Industrial Development Corporation (MIDC) is a government body based in Mumbai, Maharashtra.
What does Maharashtra Industrial Development Corporation (MIDC) do?
The Maharashtra Industrial Development Corporation (MIDC) is the Government of Maharashtra body that develops and runs industrial land across the state.
Where is Maharashtra Industrial Development Corporation (MIDC) located?
Maharashtra Industrial Development Corporation (MIDC) is located at "Udyog Sarathi", Marol Industrial Area, Mahakali Caves Road, Andheri (East), Mumbai – 400 093, Maharashtra.
What programs does Maharashtra Industrial Development Corporation (MIDC) run?
Maharashtra Industrial Development Corporation (MIDC) runs MIDC Grand Challenge and Industrial land, built-up space and shed allotment (MILAAP).
Which MIDC programme should I apply to?
It depends on how far along your startup is. Idea stage: MIDC Grand Challenge. Prototype stage: MIDC Grand Challenge. MVP stage: MIDC Grand Challenge. Early revenue stage: MIDC Grand Challenge. Growth stage: MIDC Grand Challenge. Check the programme's own eligibility before applying — several programmes are sector-specific.
Does Maharashtra Industrial Development Corporation (MIDC) take equity?
No. Maharashtra Industrial Development Corporation (MIDC) states that it takes no equity in MIDC Grand Challenge and Industrial land, built-up space and shed allotment (MILAAP).
Does Maharashtra Industrial Development Corporation (MIDC) provide funding?
Selected startups in some Maharashtra Industrial Development Corporation (MIDC) programmes can receive grant support, including MIDC Grand Challenge. Grant amounts are set per programme and cohort, and selection into a programme does not guarantee a grant — check the programme's own page for current terms.
What sectors does Maharashtra Industrial Development Corporation (MIDC) support?
Maharashtra Industrial Development Corporation (MIDC) works with startups in Aerospace & Defence, Automobiles, Chemicals, Electronics, Food Processing and Gems & Jewellery and other sectors.
How do I apply to Maharashtra Industrial Development Corporation (MIDC)?
MIDC has two very different application routes and they share almost nothing. If you want land, space or a shed to build in, that is the MILAAP portal. If you have a technology solution to an industrial infrastructure problem, that is the Grand Challenge. There is no incubation programme, no grant window and no desk space, so if that is what you are after, look elsewhere first.
Who runs Maharashtra Industrial Development Corporation (MIDC)?
Shri Deependra Singh Kushwah, IAS (Chief Executive Officer), Dr. Kunal Khemnar (Joint Chief Executive Officer - 1 (Admin)) and Smt. Varsha Thakur-Ghuge (Joint Chief Executive Officer - 2).
Who is the CEO of MIDC?
Shri Deependra Singh Kushwah, IAS is the CEO of Maharashtra Industrial Development Corporation (MIDC).
When was Maharashtra Industrial Development Corporation (MIDC) founded?
Maharashtra Industrial Development Corporation (MIDC) was founded in 1962. It is a government body.